In: Construction Works

How the Bathroom Renovation Process Works in Our Company

In this article, we will explore all the stages involved in renovating a typical Swedish bathroom of 6 square meters, which is approximately the same size as a bathroom in Estonia. This entails the following tasks: waterproofing, tiling, plumbing work and installation of fixtures, electrical installation and connection. The total number of working hours is estimated to be between 80 and 100.

The first stage is dismantling.

Dismantling walls, flooring, electrical wiring, plumbing, cutting and relocating pipes and outlets, wire insulation. Estimated time: 1-3 days for a bathroom area of 6 square meters. Required tools: jackhammer, wood saw, crowbar, hammer, screwdrivers, and trash bags.

Bathtub removal

Second Stage - Floor Preparation

To install water underfloor heating, we lay down gypsum or chipboard (wood particle board), reinforce around the perimeter, cover with plastic film, and pour concrete. The spacing for the water heating hose is 15 cm (in conjunction with the reinforcement). We secure the plumbing pipes with rigid tape. Required materials: reinforcement tape, gypsum, temporary pipe caps, reinforcement mesh, water heating tubes (diameter 16 – 22 mm), plastic film.

Preparing the floor in the bathroom

The third stage involves working with the floor, marking it, and pouring the concrete.

It is crucial to install pipes (horizontal branches) in such a way that wastewater flows by gravity. The angle of the horizontal branches must be correctly calculated, approximately 1 cm per linear meter of pipe. It is important to choose the right diameter of pipes and the slope angle, otherwise, the system will frequently malfunction. The most common material for floor screed is a cement-sand mixture, which should be thoroughly mixed with water using a drill. It is very important to wait until the screed is completely dry. The next day, the floor should be flooded with water to saturate the screed and prevent future cracking, as cracking can lead to numerous additional problems down the line.

Floor work, marking, and pouring the bathroom floor

Operating Hours: 1 Day!

Step Four: Initial Wall Preparation

We assemble the framework for wall paneling using wooden battens with a diameter of 40-45 mm. The battens are placed every 60 cm, starting from the center of the wall, and are secured to the wall with dowels.

If necessary, insulation is installed, and to prevent moisture ingress, everything is covered with a film. Regular or moisture-resistant drywall (the latter is about three times more expensive) is used: moisture-resistant drywall is installed directly near the bathtub and up to one meter on either side.

We «conceal» the pipes within the walls—construct a frame and cover it with drywall.

Initial preparation of the bathroom walls

Operating Hours: 1 Day!

The fifth stage – waterproofing the walls

Apply the primer, and after it dries in about 2 hours, apply the waterproofing layer. Use a roller or a large trowel to smooth it out. If the waterproofing material is a sheet, adhere it to the wall with a 5 cm overlap.

We apply waterproofing solution to the overlaps.

Waterproofing the bathroom walls

Working hours – 1 day (5 hours)

The sixth stage involves the required time for tiling, door frame installation, and ceiling plastering.
  • Tiling – 16 hours (2 days)
  • Installing a new door frame – 2 hours
  • Ceiling putty application – 3 hours

We prime the floor, and after it dries (2 hours), we apply the self-leveling compound.

Tile work, door frame installation, and ceiling patching in the bathroom

Seventh Stage – Floor Tiling
  • Apply the primer once more, and then install the waterproofing with a 5 cm overlap. (2 hours).
  • Laying tiles on the floor (8 hours).
Bathroom floor tiling

Eighth Stage – Completion of Work
  • We fill all the gaps between the tiles with grout, removing the excess and shaping them according to the standard to create neat joints. (5 hours)
  • We cover the floor with paper, apply putty to the ceiling, and paint it (4 hours)
  • Connecting plumbing and electrical systems (2 hours)
  • Place silicone rings in the required spots, then fill the joints between the walls and the floor with silicone. (1 hour)
  • Installing the faucet and furniture (2 hours)
Completion of bathroom renovation

Order the service right now!

  • To get started, simply fill out the easy application form on our website. One of our specialists will contact you within 24 hours.
  • For a more accurate price quote, we recommend attaching photographs and a detailed description of the property.

Advantages of Partnering with Baltic Job Service OÜ

  • We have been operating in the market since 2006.
  • All specialists possess relevant education and practical experience working on projects of varying complexity.
  • We use only high-quality, state-of-the-art tools and materials.
  • Tight Deadlines for Project Completion
  • Fair and Competitive Prices
  • Three-year warranty on all types of work

x

APPLICATION

Call or request through the website

MEASUREMENT

Site visit by the surveyor

BUDGET

Preparation and approval of the budget

AGREEMENT

Signing the contract

PERFORMANCE

Task completion